Construction Progress


Update construction for Grand Himalai May 24, 2019

Building B1 – Ceiling installation was started last week. Now 25% complete (pictures below).

Building C1 – (Above left) Ongoing interior plastering work.

Building D9 – (Above right) Work has re-commenced on this building. Interior plastering work is on-going.

Building E12 – Footing started for this middle zone building last week.

Building E40-41-F1 – (Upper zone) Stone clearance needs to be completed before work can start on footings.

(Above) Interior of building D9.

(Above) The stones which have been removed from the site, and the concrete leaning for a new tower crane base.


Update construction for Grand Himalai May 16, 2019


Update construction for Grand Himalai May 02, 2019


Update construction for Grand Himalai April 25, 2019



Update construction for Grand Himalai November 2018



Update construction for Grand Himalai October 2018



December 2017, Completion of Excavation, piling & footings for Grand Himalai lobby and Restaurant:

Construction Report Q3, 2017: